Prepare
Base
Excavate trench 200mm (8") deep and 400mm (16") wide. Place and
compact gravel to 100mm (4") depth. |
 |
First
Course
Place only standard units on gravel base. Ensure units are level from
back to front and from side to side. |
 |
Stack
Units
Stack units along wall. Coping units can be used in the wall, but
should not be stacked on other coping units without adhesive. |
 |
Placing
Coping
Place a line of adhesive in front of and behind the tongue on the second
last course. Position coping stones on top. |
 |
Finish
Wall
Fill with compacted soil to top of the wall. |